Raksan Transformers Q2 FY27 Earnings Call — Analysis (BSE: 544924)
H1 FY27 revenue and margins were pressured by a low-value government-order mix and raw-material inflation, while a ₹427 Cr order book and the Liwaspur expansion underpin the growth case.
Result quality: stable — Results context unavailable. Management sentiment: neutral.
The take
H1FY27 Revenue from operations ₹121.1 Cr . New guidance — revenue scale from the new liwa… ₹1500 Cr . New story: Capacity expansion and upcycling .
Results
H1 FY27 revenue was ₹121.1 Cr; EBITDA was ₹8.2 Cr at a 6.8% margin, and PAT was ₹4.9 Cr at a 4.1% margin, with management attributing pressure to order mix and higher input costs.
Financial highlights
| Metric | Value | Change | Basis |
|---|---|---|---|
| Revenue from operations | ₹121.1 Cr | none · H1FY27 | |
| EBITDA | ₹8.2 Cr | none · H1FY27 | |
| EBITDA margin | 6.8% | none · H1FY27 | |
| PAT | ₹4.9 Cr | none · H1FY27 | |
| PAT margin | 4.1% | none · H1FY27 | |
| Order book | ₹427 Cr | point_in_time · September 2026 · September 2026; management also referred to approximately ₹430 Cr | |
| Net worth | ₹195 Cr | point_in_time · September 2026 · As reported for H1 FY27 | |
| Debt-to-equity | 0.14x | point_in_time · September 2026 · As reported for H1 FY27 | |
| Trade receivables | −29% | none · H1FY27 · Management said receivables declined during the period; comparison base not specified |
Guidance
Management targets the Liwaspur facility entering production in FY27 and a roughly ₹1,500 Cr revenue scale in 4–5 years.
What management committed to
- The Liwaspur manufacturing facility should be completed and put into production within the current financial year. — FY27
- The Liwaspur facility is expected to increase existing power-transformer manufacturing capacity of approximately 1,350 MVA to around 3,250 to 4,000 MVA per annum following the expansion. — 3,250 to 4,000 MVA per annum, following the expansion
- Upon stabilization and optimum utilization, the expanded manufacturing capabilities are expected to provide incremental annual revenue potential of approximately 2–3 times existing revenue levels, subject to market demand, order inflows and execution timelines. — 2-3times of existing revenue levels, upon stabilization and optimum utilization
- The company is targeting around INR1500 crores of revenue from the new factory, with 4 to 5 years to reach that mark. — INR1500 crores, 4 to 5 years
- More than 60% of the transformers in the order book reported as of September 30, 2026 should be dispatched before March 31, 2027. — above 60%, FY27
- For the current financial year, the company expects approximately 30% government sales and more than 70% private-sector revenue. — 30% government sale, and 70% plus private revenue, FY27
- As a rough estimate, PAT margins will be around 11% or higher; the consultant described the deliverable as around 10% to 11% PAT margin. — around 11% or higher; between 10% to 11%, over the next 3 years to 4 years
- No major capex is planned for the coming 3 years to 4 years; any small capex will be managed through internal accruals. — the coming 3 years to 4 years
- The company is targeting a capacity of 30 MVA for IDT transformers at the new facility and said operations for units up to 30 MVA would commence immediately. — 30 MVA, effective immediately
- The new facility will begin power-transformer operations by immediately targeting 40 MVA, and the company is preparing to submit quotes for that capacity. — 40 MVA, immediately
- The company’s immediate target is to reach the 220 kV class over the next 3 years to 4 years. — 220 kV class, the next 3 years to 4 years
- In H2, approximately 70%–75% of transformer production would be copper transformers and 25%–30% aluminium transformers; management described this as a rough estimate. — 70%-75% copper transformers; 25%-30% aluminium transformers, H2FY27
Key themes
Capacity expansion and mix upgrade
How the narrative shifted
- Capacity expansion and upcycling: Management positions the Liwaspur facility as the route past current space constraints and toward higher-capacity, higher-voltage transformer production.
- Private-sector mix upgrade: Management presents the move away from small-capacity, lower-value government orders toward private-sector and higher-capacity products as a recovery in revenue quality.
- Raw-material cost volatility: Management attributed H1 margin pressure to sharp increases in oil, copper, aluminium and steel costs and said pass-through timing depends on contract terms.
- Order book and execution visibility: Management cites a substantial, mostly private-sector order book and says dispatch timing is being agreed with customers around the facility’s capacity constraints.
- Service-led competitive positioning: Management argues that delivery commitment, customer tenure and after-sales support help Raksan win business despite competition and long freight distances.
- Power infrastructure demand: Management sees conventional power, industrial infrastructure, renewables and new RDSS schemes as sources of demand for the expanded product range.
Operational commentary
- The new Liwaspur, Sonipat facility is planned at approximately 1.07 lakh square feet, with estimated investment of ₹72.58 Cr; management said it is targeting production during FY27.
- Management said existing manufacturing facilities are operating at approximately 100% capacity and generated ₹363 Cr revenue in FY26; it described space constraints as limiting further growth.
- Management reported an order book of approximately ₹427 Cr at September-end, with 85%–90% from private-sector customers and EPC companies; it later cited approximately ₹46 Cr of additional orders and an approximately ₹550 Cr order book including orders already executed in FY27.
- The company is shifting away from small-capacity aluminium distribution transformers toward higher-capacity products and private-sector business; management said current-year revenue was expected to be over 70% private-sector.
- The new facility is intended to support higher-capacity products, including IDT units up to 30 MVA and power transformers initially targeting 40 MVA; management also described a longer-term aim to reach the 220 kV class.
- Management said negotiations for projects in Nashik and other Maharashtra locations were in final stages, and that the company supplies across 17 Indian states.
- Management cited more than 20 utility, PSU and distribution-corporation approvals as part of the company’s customer and market access.
Analyst Q&A
Q. What drove the H1 revenue decline: lower realization per MVA or fewer transformers sold?
Management attributed lower revenue to a higher share of smaller-capacity aluminium B2G transformers and said transformer volumes had not declined.
Q. What margin trajectory should investors expect in H2 and FY28–FY29?
Management described price-variation clauses and gave an approximate 10%–11% PAT-margin expectation, but did not provide a clearly dated, detailed ramp or reconcile that estimate with its separate comments on private-sector margins.
Q. How much of the order book is fixed-price, and when will it be executed?
Management said approximately 10% of the approximately ₹425 Cr order book was fixed-price and estimated that over 60% of the September-end order book would be dispatched by March 31, 2027.
Q. When will the new facility be operational, and what approvals are needed for higher-capacity products?
Management targeted production in FY27 and said existing brand approvals remain valid, while new higher-capacity or project-specific work may require additional approvals.
Q. What capex is planned for FY27 and the next financial year?
The consultant said GRAP-related construction restrictions could affect timing: 80%–85% of capex was expected to be invested in FY27 if restrictions were lifted, otherwise a lower proportion could be deployed; the answer did not provide a firm next-year amount.
Q. What order inflow should investors expect next year?
Management described RDSS opportunities and tender activity as supportive and said its targets should be achievable, but gave no quantified order-inflow target.
Research and educational content only. Not investment advice.