JK Lakshmi Cem. Q2 FY27 Earnings Call — Analysis (NSE: JKLAKSHMI)
Q2 was pressured by monsoon disruption and fuel inflation, while management expects H2 pricing and demand to improve and is prioritising balance-sheet discipline over faster expansion.
Result quality: watch — Margin pressure. Management sentiment: optimistic.
The take
Q2FY27 Non-cement revenue ₹183 Cr . Guidance raised — FY30 capacity target fy30 25 million tons . But walked back — Balance sheet discipline over volume growth . New story: Geo-mix and realization optimization .
Results
Q2 volume growth was 5% and H1 volume growth was 7%; fuel cost rose to INR1.82 per 1,000 kcal from INR1.54, while power cost was 6.24 per unit versus 5.52 in Q1.
Financial highlights
| Metric | Value | Change | Basis |
|---|---|---|---|
| Volume growth | 5% | none · Q2FY27 · Q2 growth; no comparison period stated | |
| Volume growth | 7% | none · H1FY27 · H1 growth; no comparison period stated | |
| Fuel cost | INR1.82 per 1,000 kcal | none · Q2FY27 · Management cited INR1.54 as the earlier figure but did not specify its period | |
| Blended power cost | 6.24 per unit | +0.72 per unit | qoq · Q2FY27 · Compared with 5.52 in Q1FY27 |
| Non-cement revenue | ₹183 Cr | none · Q2FY27 | |
| RMC revenue | ₹86 Cr | none · Q2FY27 | |
| AAC block revenue | About ₹70 Cr | none · Q2FY27 · Management described this as an approximate figure | |
| Blended margin for non-cement businesses | 5% | none · Q2FY27 · Management's stated blended margin | |
| Clinker sales | 1,50,000 tons | none · Q2FY27 | |
| Green energy share | 48% | none · Q2FY27 · Management's stated share |
Guidance
Management expects H2 volume growth of 7%-8%, with net debt/EBITDA peaking around 2.5 by FY27-end.
What management committed to
- [JK Lakshmi Cement] has revised its capacity target from 30 million tons to 25 million tons by FY2030. — 25 million tons, FY30
- [JK Lakshmi Cement] will ensure that net debt to EBITDA does not cross 3.5 going forward. — 3.5x, ongoing
- [JK Lakshmi Cement] expects Q3FY27 fuel cost per 1,000 kcal to be around INR2 or slightly more. — INR2 per 1,000 kcal, Q3FY27
- [JK Lakshmi Cement] expects Q4FY27 fuel cost per 1,000 kcal to be around INR2.15 to INR2.2 if current conditions persist. — INR2.15-2.2 per 1,000 kcal, Q4FY27
- [JK Lakshmi Cement] expects cement price increases of INR10 per ton in November and another INR10-15 per ton in December 2026. — INR10 in Nov, INR10-15 in Dec, Q3FY27
- [JK Lakshmi Cement] is confident of matching industry volume growth of 7-8% in the second half of FY27. — 7-8%, H2FY27
- [JK Lakshmi Cement] expects to commission the Durg expansion (2.3 MTPA clinker, 1.6 MTPA cement) by March 2028. — March 2028, FY28
- [JK Lakshmi Cement] expects to commission the Northeast expansion (1.5 MTPA) around March 2029. — March 2029, FY29
Key themes
Pricing recovery and disciplined expansion
How the narrative shifted
- Geopolitical fuel & logistics cost surge: Management provided explicit fuel cost forecasts for Q3 and Q4, citing ongoing geopolitical tensions and domestic coal price increases.
- Geo-mix and realization optimization: Management continues to emphasize premium product mix and geographic consolidation to improve realizations and reduce gap with market leader.
- Capacity expansion execution (Durg, Northeast): The capacity target was cut from 30 to 25 MTPA, citing balance sheet discipline as the reason.
- Renewables and cost efficiency levers: Renewable share currently at 48%, expected to inch up to 49% with new solar in Q4.
- Seasonal demand cyclicity and pricing power: The earlier cautious stance on pass-through has shifted to a more confident outlook for price recovery.
- Proxy advisor and governance friction: Not addressed in this call.
- Balance sheet discipline over volume growth: This is a significant pivot from the prior aggressive expansion narrative.
- Competition dynamics in Northeast and East: Management discussed limited limestone reserves and their strategy to consolidate in existing markets while leveraging Northeast for future supply, noting that competition will be intense but their position is strong.
Operational commentary
- Durg expansion: management reported civil work more than 50% complete and fabrication about 20%-25% complete; the 2.3 million-ton clinker and 1.6 million-ton cement project was described as on track for March 2028.
- The 4.6 million-ton eastern expansion is planned across Durg (1.6 million tons), Madhubani (1.5 million tons) and Mejia (1.5 million tons). Management said clearances and site work are progressing at Madhubani and Mejia.
- The company has shifted planned capacity from Patratu to Mejia, citing land acquisition, timing and cost challenges linked to the Chota Nagpur Tenancy Act, and said Mejia has land and clearances in place.
- JK Lakshmi is building its Northeast presence, citing four mines and the potential to supply Northeast, North Bengal and North Bihar over time.
- Management said it is focused on trade sales for long-term consistency and is using premium products to support the price of its core product. Premium share was 27%; management expects around 27%-28%, with an effort to reach 30%.
- Management cited post-monsoon solar output, improved WHRS contribution after shutdowns and additional captive solar capacity as support for lower power costs and a higher renewable-energy share.
Analyst Q&A
Q. What is the fuel-cost outlook for Q3 and Q4?
Fuel cost is expected to be around INR2 per 1,000 kcal in Q3 and INR2.15-INR2.2 in Q4 if current conditions persist; Q4 is difficult to forecast because of volatility.
Q. How much price improvement is expected in November and December?
Management expects about INR10 in November and INR10-INR15 in December, subject to demand conditions.
Q. How will the company address the realization gap with the market leader?
Management said the gap has narrowed in some markets and cited premiumization and market-specific actions to reduce it further.
Q. What incentives have been approved for the Northeast expansion?
Management did not discuss the incentives on the call and offered to address the topic separately.
Q. What is the landed clinker cost for the Northeast plant relative to existing plants?
Management said it had not completed that calculation because the supply scenario discussed was far-fetched and an operating plan still needed to be prepared.
Q. What is the status and timing of the Durg, Madhubani and Prayagraj expansion projects?
Management provided project progress details and said all three projects are expected to be completed by March 2028 at the latest.
Q. Why was the FY30 capacity target revised from 30 million tons to 25 million tons?
The CFO said the company prioritised keeping net debt/EBITDA within prudential limits over reaching 30 million tons by FY30.
Research and educational content only. Not investment advice.