NHPC Ltd Q2 FY27 Earnings Call — Analysis (NSE: NHPC)
NHPC delivered strong Q2 growth as higher hydro generation lifted revenue and PAT, while commissioning milestones and a large project pipeline underpin further capacity-led growth.
Result quality: stable — Results context unavailable. Management sentiment: optimistic.
The take
Q2FY27 Revenue from operations ₹4,482 Cr ( +33% YoY YoY ) . New guidance — FY27 subansiri lower project additio… 2 more units . New story: Hydro capacity commissioning .
Results
Q2FY27 revenue ₹4,482 Cr +33% YoY and PAT ₹1,549 Cr +52%; generation rose 17% to 13,935 MUs and PAF improved to 92.24%.
Financial highlights
| Metric | Value | Change | Basis |
|---|---|---|---|
| Revenue from operations | ₹4,482 Cr | +33% YoY | yoy · Q2FY27 · Compared with ₹3,365 Cr in Q2FY26 |
| PAT | ₹1,549 Cr | +52% YoY | yoy · Q2FY27 · Compared with ₹1,021 Cr in Q2FY26 |
| Generation | 13,935 MUs | +17% YoY | yoy · Q2FY27 · Compared with 11,870 MUs in Q2FY26 |
| Plant availability factor | 92.24% | +14% YoY | yoy · Q2FY27 · Compared with 78.58% in Q2FY26; management stated the increase as about 14% |
| Revenue from operations | ₹8,291 Cr | +26% YoY | yoy · H1FY27 · Compared with ₹6,579 Cr in H1FY26 |
| PAT | ₹2,645 Cr | +27% YoY | yoy · H1FY27 · Compared with ₹2,086 Cr in H1FY26 |
| Generation | 23,741 MUs | +14% YoY | yoy · H1FY27 · Compared with 20,866 MUs in H1FY26 |
| Plant availability factor | 86.67% | +6% YoY | yoy · H1FY27 · Compared with 81.10% in H1FY26; management stated the increase as about 6% |
| Finance cost | ₹556 Cr | +₹278 Cr | yoy · Q2FY27 · Compared with ₹278 Cr in Q2FY26 |
| Trade receivables | ₹4,283 Cr | point_in_time · Q2FY27 · As of September 30, 2026; includes ₹1,573 Cr unbilled debtors | |
| Trade receivables | ₹1,159 Cr | point_in_time · Q2FY27 · As of November 3, 2026, as stated in Q&A |
Guidance
Management targets ₹14,300 Cr consolidated capex in FY27 and expects ₹14,000–15,000 Cr annually from next year.
What management committed to
- NHPC is targeting to commission two more units of [Subansiri Lower Project] during the current financial year. — 2 more units, FY27
- The remaining one unit of [Subansiri Lower Project] is expected to be commissioned by June 2027. — 1 unit, Q1FY28
- The full impact of [Subansiri Lower Project] would be largely in FY28, with full top line from FY29 onwards. — FY29
- NHPC does not anticipate any further increase in the anticipated cost of [Subansiri Lower Project]. — Rs. 30,072 Crore
- [Dibang Multipurpose Project] is scheduled for completion in February 2032, and NHPC is 100% sure it will achieve this date without any fail. — 2,880 MW, FY32
- NHPC does not anticipate any further increase in the estimated cost of [Dibang Multipurpose Project]. — Rs. 31,876 Crore
- [Teesta-VI HEP] is expected to be commissioned in September 2029. — 500 MW, Q2FY30
- [Uri-I Stage-II HEP] is scheduled to be completed in November 2029. — 240 MW, FY30
- [Dulhasti Stage-II HEP] is scheduled to be completed in November 2029. — 260 MW, FY30
- [Rangit-IV HEP] is expected to be commissioned by December 2026. — 120 MW, Q3FY27
- [Pakal Dul HEP] is expected to be fully commissioned by June 2027; NHPC is targeting two units by March 2027. — two units, Q1FY28
- NHPC is targeting commissioning of all units of [Kiru HEP] by March 2027. — all the units, Q4FY27
Key themes
Hydro commissioning and capacity growth
How the narrative shifted
- Hydro capacity commissioning: Management positioned commissioning at Subansiri Lower and the return of Teesta-V as the main drivers of higher generation and earnings.
- Large hydro project execution: Management emphasized progress across a broad construction portfolio, pairing project-level progress updates with firm completion schedules.
- Hydro pipeline expansion: NHPC is advancing new hydro projects through approvals, tendering, and early construction, with project execution dependent in some cases on government approvals.
- Renewables and PPA discipline: Management remains interested in renewable growth but is reconsidering plain-vanilla solar in favor of different configurations and does not want to build without contracted demand.
- Storage and power configuration: Pumped storage and solar-plus-storage are presented as ways to address peak-hour needs and support a more saleable renewable portfolio.
- Renewable evacuation constraints: Management attributed solar project delays and uncertainty around new PPAs to connectivity, evacuation, and changing state demand patterns.
- Capacity-led earnings and funding: Management argued that upcoming commissioning will lift EBITDA and that operating cash generation and internal resources can support the planned capex and equity needs.
- Receivables collection discipline: Despite the September quarter-end receivables balance, management emphasized subsequent collections and payment rules as evidence that recoverability is under control.
Operational commentary
- Subansiri Lower has commissioned five of eight 250 MW units, totaling 1,250 MW; two further units are targeted in FY27 and the final unit by June 2027.
- Teesta-V resumed commercial operations in July 2026 after restoration from the 2023 flash flood; it generated 859 MUs in Q2FY27.
- Pakal Dul was 89% physically complete, Kiru 92%, and Rangit-IV 98%; reservoir filling was planned for Pakal Dul and Kiru, and Rangit-IV had begun reservoir filling.
- NHPC reported progress across its larger construction pipeline: Dibang major contracts have been awarded; Teesta-VI was 74% physically complete; Kwar was 42% complete; Ratle was 33% complete and dam concreting began in November.
- Etalin is progressing through approval and tendering processes; management said all clearances had been obtained and the PIB process was initiated.
- NHPC has 18 GW of pumped-storage projects at DPR/PFR stage and is also pursuing the 640 MW Indira Sagar–Omkareshwar PSP.
- Connectivity and evacuation constraints are delaying some solar projects; management described a shift toward solar-plus-storage and other configurations, and said it does not want to build projects without PPAs.
Analyst Q&A
Q. When is the Parbati-II final tariff order expected, and what revenue and profit contribution could follow?
Management said the next hearing was scheduled for November 11 and expected it to be the final hearing, with an order expected afterward. It outlined approximate full-run revenue of ₹2,400 Cr and PAT of ₹680 Cr based on regulated equity and baseline ROE.
Q. What is the status of the Subansiri Lower tariff petition and any under-recovery?
The tariff petition covers all units and has been updated for four commissioned units; the fifth-unit update was in progress. The hearing was over and an interim tariff order was expected soon. Revenue was being booked at 80% of the tariff petition.
Q. What is driving the higher receivables balance, and when will it normalize?
Management said total receivables were ₹1,159 Cr on November 3, with only ₹6 Cr more than 45 days overdue, and attributed timely recovery to sector payment rules and collection discipline.
Q. How should investors think about debt servicing, future EBITDA, capex, and equity funding?
Management distinguished debt associated with operating assets from construction projects, indicated EBITDA could reach about ₹10,000 Cr after capacity additions, guided to ₹14,300 Cr FY27 capex and ₹14,000–15,000 Cr annual capex thereafter, and said internal resources would cover equity needs.
Q. What is the plan for renewable capacity, given connectivity constraints and uncertainty over long-term PPAs?
Management said it was considering different power configurations, including solar-plus-storage, expected further PPAs for 5,000–7,070 MW, and did not want to construct projects without a PPA. It did not provide a firm overall MW build target.
Q. Will transmission evacuation be available for planned Arunachal hydro projects?
Management said the transmission master plan was ready and that transmission line procurement is handled through tariff-based competitive bidding aligned with project commissioning schedules; it stated there was no evacuation problem for the planned Arunachal projects.
Q. Has the consideration for transferring Etalin from SJVN been paid?
Management said it had not been paid and would be paid after the PIB approval, which it expected shortly.
Research and educational content only. Not investment advice.