L&T Wins 300 MW/900 MWh BESS Order in Gujarat, Extending a Run of Multi-Sector Order Intake
On 25 November 2026, Larsen & Toubro (NSE: LT, BSE: 500510) informed the exchanges that its Renewables business, together with L&T Electronic Products & Systems, had secured an order to develop a 300 MW/900 MWh Battery Energy Storage System (BESS) at Khavda, Gujarat. The company classifies the order as ‘Significant’, which it defines as ₹1,000–2,500 crore (BSE filing, 25 Nov 2026).
On 25 November 2026, Larsen & Toubro (NSE: LT, BSE: 500510) informed the exchanges that its Renewables business, together with L&T Electronic Products & Systems, had secured an order to develop a 300 MW/900 MWh Battery Energy Storage System (BESS) at Khavda, Gujarat. The company classifies the order as ‘Significant’, which it defines as ₹1,000–2,500 crore (BSE filing, 25 Nov 2026).
This disclosure is the latest in a sequence of order announcements L&T has submitted to BSE since July 2026, covering domestic and international projects across energy, infrastructure, and heavy engineering.
A flurry of orders across verticals and geographies
L&T’s exchange filings over the past five months describe contracts ranging from metals plants to offshore platforms. The following is a selection, drawn from the company’s own announcements:
- 20 July 2026: Multiple ‘Mega’ orders (₹5,000–10,000 Cr) from domestic metals and mining companies—an 18 MTPA iron ore handling plant in Chhattisgarh, a steel plant expansion in West Bengal, and a zinc processing plant.
- 24 July 2026: ‘Large’ international orders (₹1,000–2,500 Cr each) from Africa’s Dangote Group for refinery and fertiliser equipment, plus process-equipment orders from Japan, Spain, the US, and Brazil.
- 28 July 2026: A Framework Cooperation Agreement with TenneT for a 2 GW HVDC offshore wind programme covering up to six projects (including IJmuiden Ver Alpha, Nederwiek 1, Nederwiek 3, LanWin 5) in the Netherlands and Germany.
- 4 August 2026: An ‘ultra-mega’ contract (>₹15,000 Cr) from ADNOC Offshore for EPCIC of multiple offshore facilities in the Middle East.
- 17 August 2026: Another ultra-mega (>₹15,000 Cr) offshore EPCIC order from a Middle Eastern client.
- 24 August 2026: An ultra-mega gas-compression EPC contract in the Middle East (>₹15,000 Cr).
- 25 August 2026: A 6 GWh BESS EPC contract in the Middle East (₹1,000–2,500 Cr).
- 5 October 2026: ‘Mega’ power transmission and distribution EPC contracts (₹5,000–10,000 Cr combined) in Saudi Arabia, the UAE, and India.
- 7 October 2026: A Limited Notice to Proceed (LNTP) for the main plant package of a 2×800 MW ultra-supercritical thermal project at Chandrapura, Jharkhand, valued in the ₹1,000–2,500 Cr band.
- 19 October 2026: An LNTP for the passenger terminal and landside infrastructure of the new greenfield Tashkent International Airport, Uzbekistan.
Order inflow steps up, but margins feel the mix
The Q1FY27 results filing (28 July 2026) reported order inflow of ₹1,08,014 crore, up 14% year-on-year, while consolidated revenue stood at ₹67,942 crore (+7% YoY) and PAT at ₹4,123 crore (+14% YoY). The press‑release EBITDA margin narrowed to 9.0%, down 90 basis points YoY.
For Q2FY27, the filing dated 27 October 2026 showed consolidated revenue of ₹78,749.94 crore (+16% YoY) and PAT attributable to owners of ₹5,202.10 crore (+33% YoY). EBITDA margin slipped further to 8.7%, with the company citing execution mix and cost pressures in the commentary.
Portfolio reshaping continues
Alongside operational momentum, L&T’s filings point to structural moves:
- On 25 June 2026, the company completed the sale of its wholly owned subsidiary Nabha Power Limited to Torrent Power, receiving ₹3,632.35 crore (after closing adjustments).
- A Scheme of Arrangement to demerge the realty business into L&T Realty Properties moved through the NCLT process; the shareholder meeting was held on 4 August 2026.
- In August 2026, L&T transferred its Data Center & Cloud Services Business and its entire stake in L&T Network Services to its subsidiary Vyoma.AI for a total consideration of ₹1,430 crore, settled via Vyoma equity shares.
- On 9 September 2026, L&T raised ₹500 crore via tokenised bonds, becoming the first private‑sector corporate to use SEBI’s blockchain‑based framework.
What the filings say comes next
Several projects are yet to convert to full construction. The Chandrapura thermal plant LNTP (7 Oct 2026) states that the “full Notice to Proceed will be issued after environmental clearances and the LNTP period.” The Tashkent airport LNTP (19 Oct 2026) notes that the full notice is “expected once contractual conditions precedent are met.” The realty demerger scheme awaits final regulatory approvals.
Alpha Inflection is research infrastructure, not investment advice. We are not SEBI‑registered investment advisers. Everything above is compiled from public corporate filings, with sources cited. Do your own research.
The filing evidence
| Date | What the filing said | Detail | Source |
|---|---|---|---|
| 20 Jul 2026 | L&T wins multiple mega orders (₹5,000-10,000 Cr) for metals and minerals business from domestic companies | L&T's Metals & Minerals vertical secured multiple EPC orders from leading domestic metals and mining companies: an iron ore handling plant (18 MTPA) for a public sector iron ore producer in Chhattisgarh, design & build and balance of plant packages for a steel plant expansion (2.5 to 7.1 MTPA) for a Navratna company in West Bengal, and a zinc processing plant for a major private sector metals producer. The orders are classified as 'Mega' (₹5,000-10,000 Cr). | filing |
| 24 Jul 2026 | L&T Heavy Engineering wins multiple large international orders (₹1,000–2,500 Cr each) for process equipment from Dangote Group and other global clients across Asia, Africa, North America, South America, and Europe. | L&T's Heavy Engineering division secured a series of orders classified as 'Large' (₹1,000–2,500 Cr each) from international clients. The largest includes orders from Africa's Dangote Group for a mega refinery and multi-train fertiliser expansion in Nigeria and Ethiopia, involving the world's largest Fluid Catalytic Cracking Reactor Regenerator Package and critical urea/ammonia equipment. Additional orders include a repeat order from a Japanese customer for heat exchangers and absorbers for an LNG project in Canada, and orders from Spain, the US, and Brazil for coke drums, fractionator columns, and heat exchangers. | filing |
| 27 Jul 2026 | L&T's Residential, Commercial Buildings & Factories business wins major ₹1,000–2,500 Cr order for a large-scale housing redevelopment project in Mumbai. | Larsen & Toubro's RCF vertical has secured a major order (classified as ₹1,000–2,500 Cr) from a reputed client for the turnkey design and construction of 26 high-rise residential towers (120 m each) in Mumbai. The project will use L&T's large-wall panel precast technology involving offsite manufacturing and onsite assembly. | filing |
| 28 Jul 2026 | L&T secures ultra-mega framework agreement with TenneT for 2 GW offshore wind programme covering 4 HVDC projects in Netherlands and Germany. | L&T, in consortium with Hitachi Energy, has signed a Framework Cooperation Agreement with TenneT for a 2 GW HVDC offshore wind programme. The framework covers up to six projects, including two ongoing (IJmuiden Ver Alpha and Nederwiek 1) and two new projects (Nederwiek 3 in the Netherlands and LanWin 5 in Germany), totalling 8 GW transmission capacity. L&T will execute offshore converter platforms and associated infrastructure under EPCI scope. | filing |
| 29 Jul 2026 | L&T wins a major (~₹1,000-2,500 Cr) EPC order from Kuwait Oil Company for Jurassic Light Oil export facilities and crude handling upgrades. | L&T Energy Hydrocarbon Onshore business secured a major engineering, procurement and construction (EPC) order from Kuwait Oil Company (KOC) for new crude oil storage tanks (six tanks of 618,000 barrels each), associated facilities, pipelines, and upgrades to Kuwait's existing crude loading and export network, on a lump sum turnkey basis. | filing |
| 4 Aug 2026 | L&T's energy hydrocarbon offshore arm wins an ultra-mega order (value > ₹15,000 Cr) from ADNOC Offshore for development of multiple offshore facilities in the Middle East. | Larsen & Toubro's subsidiary LTEH Offshore has secured an ultra-mega contract from ADNOC Offshore for the development of multiple offshore facilities in the Middle East, with LTEH leading a consortium and handling engineering, procurement, construction, installation, and commissioning (EPCIC) as well as upgrades to existing facilities. | filing |
| 7 Aug 2026 | L&T's hydrocarbon offshore arm wins major orders (₹1,000–2,500 Cr) from ONGC for pipeline replacement and well head platform projects off India's west coast. | L&T Energy Hydrocarbon Offshore secured multiple orders from ONGC for the Pipeline Replacement Project (PRP-X) involving EPCIC of subsea pipelines and associated modifications, and a project for EPCIC of four Well Head Platforms off India's west coast. | filing |
| 17 Aug 2026 | L&T secures an ultra-mega (over ₹15,000 Cr) offshore EPCIC order from a Middle Eastern client | L&T Energy Hydrocarbon Offshore has received an ultra-mega order (value > ₹15,000 Cr) from a prestigious Middle Eastern client for the development of multiple offshore facilities, covering engineering, procurement, construction, installation, and commissioning. | filing |
| 20 Aug 2026 | L&T, in consortium with Mitsubishi Heavy Industries, wins a large (₹1,000–2,500 Cr) order for an Automated People Mover System at Dubai's Al Maktoum International Airport. | L&T's Transportation Infrastructure business vertical, in consortium with Japan's Mitsubishi Heavy Industries, secured a large turnkey order to design and build the Automated People Mover (APM) System for Phase 1 of Al Maktoum International Airport in Dubai. The scope includes design, construction, supply, testing, commissioning and operational readiness of guideways, traction substations, power distribution, signalling, telecom, platform screen doors and depot equipment. | filing |
| 24 Aug 2026 | L&T signs ultra-mega (>₹15,000 Cr) gas compression EPC contract in the Middle East | L&T Energy Hydrocarbon Onshore signed a contract for the engineering, procurement and construction of gas compression plants, including associated utilities and substations, for a Middle Eastern client. | filing |
| 25 Aug 2026 | L&T's renewables business wins a major order (₹1,000-2,500 Cr) for a 6 GWh Battery Energy Storage System in the Middle East. | L&T's renewables vertical secured a major EPC contract to develop three BESS projects with a combined 6 GWh capacity in the Middle East, including grid interconnections and substations. | filing |
| 9 Sept 2026 | L&T Energy Hydrocarbon Offshore wins a large offshore EPCIC order from ONGC valued between ₹1,000–2,500 crore. | L&T's offshore arm secured a large order from ONGC for the Additional Development of Ratna–I (ADR I) and NLM-14 project off India's west coast, involving engineering, procurement, construction, installation, and commissioning of offshore facilities and subsea infrastructure. | filing |
| 30 Sept 2026 | L&T Transportation Infrastructure vertical secures twin contracts from Dubai's RTA for the development of Latifa Bint Hamdan Corridor. | L&T's Transportation Infrastructure vertical has formally executed twin contracts (one large, one significant) with Dubai's Roads and Transport Authority (RTA) for the Latifa Bint Hamdan Corridor development. The scope includes new roads, bridges, tunnels, an interchange, and a cycling track to improve connectivity and reduce travel time. Completion is scheduled by end of 2028. | filing |
| 5 Oct 2026 | L&T's Power Transmission & Distribution vertical has secured multiple EPC orders in India, Saudi Arabia, and the UAE, classified as 'Mega' (₹5,000–₹10,000 crore). | L&T announced its PT&D vertical won multiple EPC contracts: in Saudi Arabia (380 kV transmission/substations for renewable energy evacuation), the UAE (132/11 kV substations and cabling), and India (transmission system for a private developer in Visakhapatnam). The combined value is classified as 'Mega' (₹5,000–₹10,000 crore). | filing |
| 7 Oct 2026 | L&T Energy CarbonLite Solutions secures LNTP for 1,600 MW ultra-supercritical thermal power plant at Chandrapura, Jharkhand, in a Major order value bracket of ₹1,000-2,500 crore. | L&T's Energy CarbonLite Solutions business vertical received a Limited Notice to Proceed (LNTP) from DVC CIL Power Private Ltd (a joint venture of Damodar Valley Corporation and Coal India Ltd) for the main plant package of the 2x800 MW ultra-supercritical thermal power project at Chandrapura, Jharkhand. L&T's scope includes design, engineering, manufacturing, supply, erection, testing, and commissioning of Boilers, Steam Turbines, Generators, and Electrostatic Precipitators, along with associated mechanical, electrical, control & instrumentation and civil works. The full Notice to Proceed will be issued after environmental clearances and the LNTP period. | filing |
| 19 Oct 2026 | L&T commences initial pre-construction activities for ultra-mega New Tashkent International Airport project after securing Limited Notice to Proceed. | L&T's Public Spaces, Airports & Health business vertical has received a Limited Notice to Proceed (LNTP) from the PPP consortium for the EPC contract to build the passenger terminal and associated landside infrastructure of the new greenfield Tashkent International Airport in Uzbekistan. The LNTP enables L&T to start initial engineering, detailed design, procurement preparation, and other pre-construction activities. The full Notice to Proceed is expected once contractual conditions precedent are met. | filing |
| 25 Nov 2026 | L&T wins a significant order (₹1,000-2,500 crore) for a 300 MW/900 MWh Battery Energy Storage System in Gujarat. | L&T's Renewables business and L&T Electronic Products & Systems won an order to develop a 300 MW/900 MWh BESS at Khavda, Gujarat. The order is classified as 'Significant' (₹1,000-2,500 crore). | filing |
| 21 Jun 2026 | Larsen & Toubro's wholly owned subsidiary Vyoma.AI Limited incorporates a new wholly owned step-down subsidiary, LTN Compute Private Limited, to establish AI compute infrastructure. | Larsen & Toubro announced that its wholly owned subsidiary, Vyoma.AI Limited, has incorporated a new wholly owned subsidiary named LTN Compute Private Limited (LTNCPL) on June 20, 2026, with an authorized capital of Rs. 1,00,000, which has been fully subscribed in cash. | filing |
| 24 Jun 2026 | L&T receives NCLT order to convene shareholder meeting to approve the scheme of arrangement for demerger of its realty business into L&T Realty Properties. | Larsen & Toubro received a certified copy of the NCLT order dated June 12/16, 2026, directing it to hold an electronic shareholder meeting within 60 days to seek approval for the proposed scheme of arrangement with L&T Realty Properties. | filing |
| 25 Jun 2026 | Larsen & Toubro completes divestment of its wholly owned subsidiary Nabha Power Limited to Torrent Power for ₹3,632.35 crore. | L&T announced the completion of the sale of 100% equity and convertible instruments in Nabha Power Limited (NPL) to Torrent Power, receiving ₹3,632.35 crore in consideration (after closing adjustments). L&T's subsidiary retains 0.1% non-convertible redeemable preference shares valued at ₹157.92 crore, and NPL ceases to be a subsidiary. | filing |
| 29 Jun 2026 | Larsen & Toubro publishes notice for NCLT convened meeting on August 4, 2026 to consider Scheme of Arrangement with L&T Realty Properties. | Larsen & Toubro Limited (L&T) published newspaper advertisements informing equity shareholders of an NCLT-convened meeting to be held on August 4, 2026 via video conferencing to consider and approve a Scheme of Arrangement between L&T and its subsidiary L&T Realty Properties Limited under Sections 230-232 of the Companies Act, 2013. | filing |
| 28 Jul 2026 | Q1FY27: Revenue ₹67,942 Cr (+7% YoY, decelerating from +15.5% in Q1FY26), PAT ₹4,123 Cr (+14% YoY, driven by lower finance costs and other income), EBITDA margin contracted 90bps YoY to 9.0% amid cost pressures and revenue mix shift. | filing | |
| 28 Jul 2026 | Q1FY27: Revenue ₹67,942 Cr (+6.7% YoY), PAT ₹4,123 Cr (+14.0% YoY); Order inflow robust at ₹108,014 Cr (+14%) led by Infrastructure & Utilities and Energy-Green; EBITDA margin (XBRL) stable at 12.5% (+45bps YoY) but press-release EBITDA margin declined to 9.0% (-90bps); other income at 34.3% of PBT flags earnings quality. | filing | |
| 28 Jul 2026 | L&T Q1FY27: revenue +7% YoY to ₹67,942 Cr, PAT +14% to ₹4,123 Cr; order inflow +14% to ₹1.08 lakh Cr; operating EBITDA margin contracted 90bps to 9.0%, but other income and lower finance costs lifted bottom line. | filing | |
| 28 Jul 2026 | L&T's Senior Vice President & IC Head - Transportation Infrastructure IC, Mr. V. Sukumar Hebbar, resigns effective July 27, 2026. | Mr. V. Sukumar Hebbar, Senior Vice President & IC Head - Transportation Infrastructure IC, resigned from Larsen & Toubro with effect from the close of business hours on July 27, 2026, and ceased to be a Senior Management Personnel. | filing |
| 3 Aug 2026 | Earnings call transcript filing for Q1FY27 released; full transcript available on company website, no financial or operational details in this document. | filing | |
| 11 Aug 2026 | L&T transfers its Data Center & Cloud Services Business and entire stake in L&T Network Services Private Limited to wholly owned subsidiary Vyoma.AI Limited for total consideration of ₹1,430 crore via equity shares. | Larsen & Toubro has executed a Business Transfer Agreement to transfer its Data Center and Cloud Services Business to its wholly owned subsidiary Vyoma.AI Limited for ₹1,400 crore, and a Share Purchase Agreement to sell its entire stake in L&T Network Services Private Limited to Vyoma for ₹30 crore, both to be settled through issuance of Vyoma equity shares. The transactions are expected to close by October 31, 2026. | filing |
| 9 Sept 2026 | L&T becomes India's first private sector corporate to issue a ₹500 crore tokenised bond under SEBI's blockchain-based framework. | Larsen & Toubro raised ₹500 crore via tokenised bonds with a 3-year tenure, using SEBI's new Distributed Ledger Technology framework, with settlement via a Central Bank Digital Currency wallet. | filing |
| 7 Oct 2026 | L&T promotes four officials to Senior Vice President and categorises them as Senior Management Personnel. | L&T promoted four senior employees — Dr C Jayakumar (Corporate HR), Suresh Kumar Narang (CarbonLite Solutions & CEO LMB), S Ramkumar (Transportation Infrastructure IC), and Sriraman T (Residential, Commercial Buildings & Factories IC) — to Senior Vice President and designated them as Senior Management Personnel, effective 1 July 2026. | filing |
| 27 Oct 2026 | Consolidated revenue rose 16% YoY to ₹78,749.94 crore and PAT attributable to owners rose 33% to ₹5,202.10 crore, but EBITDA margin contracted to 8.7% as execution mix and cost pressures offset record order momentum. | filing | |
| 2 Nov 2026 | Earnings call transcript body not provided in the exchange filing. | filing |
Quick answers
- What did Larsen & Toubro disclose?
- On 25 November 2026, Larsen & Toubro (NSE: LT, BSE: 500510) informed the exchanges that its Renewables business, together with L&T Electronic Products & Systems, had secured an order to develop a 300 MW/900 MWh Battery Energy Storage System (BESS) at Khavda, Gujarat.
- What are the key numbers?
- The Q1FY27 results filing (28 July 2026) reported order inflow of ₹1,08,014 crore, up 14% year-on-year, while consolidated revenue stood at ₹67,942 crore (+7% YoY) and PAT at ₹4,123 crore (+14% YoY). The press‑release EBITDA margin narrowed to 9.0%, down 90 basis points YoY.
Research and educational content only. Not investment advice. Drafted from regulatory filings and published automatically — see our editorial policy.